2017/2018 Cruise Schedule-

 

Fall Bottom Trawl Survey - Revised 9-18-2017

The fall bottom trawl survey is now fully staffed. Spring cruise staffing will begin in late January, 2018.

Survey/Dates
Days at Sea
Survey Area
Leg 1: Oct 16 - Nov 3
19
S New England - Georges Bank
Leg 2: Nov 7 - Nov 20
14
Gulf of Maine


Spring Bottom Trawl Survey (NOAA Ship Henry B. Bigelow ) -

Staffing begins in late January, 2018

 

Sea Scallop / Integrated Benthic Survey (R/V Hugh R. Sharp) -

Staffing begins the end of March, 2018.

 

Atlantic Surf Clam / Ocean Quahog Survey (R/V E.S.S. Pursuit) -

Staffing begins the end of June, 2018.

 

 

 