eMOLT projected 2002 timeline:
Feb 1st  at least two Microcats deployed
Feb 15th All phase II participants decided
Feb 15th Water Samplers ordered
March 1st eMOLT at Maine Fish Forum
March 4th Remaining Microcats ordered
March 4th All 5 Microcats Deployed
March 10th Phase III Draft I
March 17th Phase III Final
April 14-18th eMOLT at Nat.Shllfsh Soc meet.
April 30th Remaining Microcats Deployed